Slavnostní zahájení významného investičního projektu – „Kalové hospodářství ČOV Brno – Modřice“
Investor: Brněnské vodárny a kanalizace, a.s.
Construction contractor: OHLA ŽS, a.s.
Location: Brno
Characteristics:
The purpose of the construction is to convey drinking water to the individual properties and wastewater collection in Solniční street from Husova street to Moravské náměstí and in Opletalova street.
Old, technically unsatisfactory parts of the water supply and sewage system, past their service life, were replaced.The project implementation resulted in increased safety of drinking water supply and sewage and rainwater collection as well as reduction in the risk of possible accidents. Given the depth of the installation, the sewers were laud using trenchless technology - classic tunnelling.
Basic capacities:
• sewer reconstruction ca. 397 m of sewerage, of which ca. 211.0 m tunnelling
• reconstruction of house drains ca. 260.0 m
• reconstruction of water mains and connections
• water main relocation, steam supply and communication cables
Work provided by AQUATIS:
Documentation for zoning permit, building permit and detail design
Detail design documentation
Designer’s supervision
As-built documentation